11/28 - 12/8


  • Steel/Deck Erection (18 Metal Decking, 18&19 framing)
  • Slab on Deck reinforcements and MEP penetrations (L16 and L17)
  • Concrete Slab on Deck Placements (L15 North and L16 South)
  • Continue Intumescent Paint & Spray Fireproofing of lower levels (through L13)
  • Continue prep for curtainwall through L17
  • Continue MEP riser installations in building core

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • Permanent Power Install - Eversource

Upcoming Holidays:

  • Christmas Day: Monday December 25, 2023