11/06 - 11/17


  • Complete Concrete Placement through Level 15
  • Continue Intumescent Paint & Spray Fireproofing of lower levels (through Level 12)
  • Continue prep for curtainwall through Level 16
  • Eversource Permanent Power installation @ Congress Street
  • Continue MEP riser installations in building core through Level 11

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • Concrete pour @ pedestrian bridge is in planning phase with MassDOT

Upcoming Holidays: