10/30 - 11/10


  • Steel framing complete through roof
  • Install Monument Stair between Levels 01-02
  • Complete Concrete Placement through Level 14
  • Continue Intumescent Paint & Spray Fireproofing of lower levels (through Level 11)
  • Continue prep for curtainwall through Level 15
  • Eversource Permanent Power installation @ Congress Street: awaiting confirmation of timing.
    • Work expected to be complete before November 15th
  • Continue MEP riser installations in building core through Level 11

Night & Weekend Work:

  • Overnight cut & cap of water service (Seaport Hotel) was completed Monday 10/30
  • Overnight cut & cap of fire protection service (Seaport Hotel) is TBD.
  • Saturday Day Shift Work to be requested on case-by-case basis.

 

Upcoming Holidays:

  • Thanksgiving: Thursday November 23, 2023