<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=459021408546817&amp;ev=PageView&amp;noscript=1">
Contact
Aug 11, 2023

08/07 - 08/18


  • Complete Steel Framing & Decking through Level 09
  • Complete Concrete Placement through Level 07
  • Excavation for Basement along Congress Street
  • Start Spray Fireproofing of lower levels
  • Form & pour tree pits + slab for Triangle Parcel landscape
  • Continue hardscape work @ WTC Ave
  • See night/weekend schedule below for look-ahead related to traffic & noise impacts.

Night & Weekend Work:

  • No road / lane closures during Sumner Tunnel Rehabilitation Project (July 1 – September 1)
  • Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected
  • Eversource work @ Haul Rd (back of house Omni Hotel): awaiting final work from Eversource (TBD)