Aug 17, 2023

08/14 - 08/25


  • Complete Steel Framing & Decking through Level 10
  • Complete Concrete Placement through Level 07
  • Start concrete @ Auditorium seating
  • Continue excavation for Basement along Congress Street
  • Continue spray Fireproofing of lower levels
  • Continue prep for landscape @ Triangle Parcel & WTC Ave
  • See night/weekend schedule below for look-ahead related to traffic & noise impacts.

Night & Weekend Work:

  • No road / lane closures during Sumner Tunnel Rehabilitation Project (July 1 – September 1)
  • Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected

Upcoming Holidays:

  • Labor Day - Monday September 4th