Aug 31, 2023

08/28 - 09/08


  • Complete Steel Framing & Decking through Level 12
  • Complete Concrete Placement through Level 08
  • Pour concrete @ Basement
  • Continue spray Fireproofing of lower levels
  • Continue prep for landscape @ Triangle Parcel & WTC Ave
  • Continue installation of intumescent paint
  • Continue installation of construction hoist @ WTC Avenue


Night & Weekend Work:

  • No road / lane closures during Sumner Tunnel Rehabilitation Project (July 1 – September 4)
  • Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected.

Upcoming Holidays:

  • Labor Day - Monday September 4th