Sep 14, 2023

09/11 - 09/22

  • Complete Steel Framing & Decking through Level 13
  • Complete Concrete Placement through Level 09
  • Pour concrete @ Basement
  • Continue spray Fireproofing of lower levels
  • Continue prep for landscape @ Triangle Parcel & WTC Ave
  • Continue installation of intumescent paint
  • Continue installation of construction hoist @ WTC Avenue

Night & Weekend Work:

  • Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected
  • Eversource Permanent Power installation @ Congress Street: awaiting confirmation of timing.
  • Fire Protection piping in Congress Street @ Triangle Parcel: 10pm-4am, Monday-Wednesday nights.
  • Pedestrian Bridge Steel welding: Thursday 9/14 (11pm-5am). Ramp F closed to traffic.