Patriots’ Day / Marathon Monday (04/17): No work on site. Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at...
Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at Level 03. Pour tower core slab Levels 04-05 Continue...
Continue below-grade work along west and north of A-2 site. Continue assembly of East arch (alongside WTC Ave). Continue steel assembly / detailing at Levels...
Continue below-grade work along west and north of A-2 site. Continue assembly of East arch (alongside WTC Ave). Continue steel assembly / detailing at Levels...
Demobilize core climber. Continue below-grade work along west and north of A-2 site. Prepare for assembly of East arch (alongside WTC Ave). Continue...