Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...
Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...
Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at Levels 2 - 3. Continued below-grade work throughout...