<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=459021408546817&amp;ev=PageView&amp;noscript=1">
Contact

Construction Updates

FEATURED STORY

6/17/24 - 6/28/24

  • Penthouse- Framing, Equipment- Connections/Rough MEP Install
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • Triangle Geofoam...

FILTER BY

Jun 15, 2023

06/12 - 06/23

Continue Level 04 framing Continue steel detailing at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend work for...
Jun 8, 2023

06/05 - 06/16

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend...
Jun 1, 2023

05/29 - 06/09

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend...
May 25, 2023

05/22 - 06/02

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) See night/weekend work for Pedestrian Bridge information ...
May 18, 2023

05/15-05/26

Continue Levels 03-04 framing Continue install of overhead protection work at highway ramp Continue steel assembly / detailing on Triangle Parcel ...
May 11, 2023

05/08-05/19

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Complete detailing of...
May 4, 2023

05/01-05/12

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...
Apr 26, 2023

04/24-05/05

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...
Apr 26, 2023

04/03-04/13

Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at Levels 2 - 3. Continued below-grade work throughout...