Oct 5, 2023

10/02 - 10/13

  • Complete Steel Framing & Decking through Level 16
  • Complete Concrete Placement through Levels 11-12
  • Continue Intumescent Paint & Spray Fireproofing of lower levels (through Level 06)
  • Continue prep for landscape @ Congress Street & WTC Ave
  • Continue prep for curtainwall through Level 13
  • Eversource Permanent Power installation @ Congress Street: awaiting confirmation of timing.
  • Water utilities work to start approx. 10/10 outside Seaport West (daytime hours).


Night & Weekend Work:

  • Saturday Day Shift Work to be requested on case-by-case basis. 
  • Fire Protection piping in Congress St @ Triangle Parcel: complete
  • Pedestrian Bridge Steel welding: complete

 

Upcoming Holidays:

  • Monday October 9th: Columbus Day.