<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=459021408546817&amp;ev=PageView&amp;noscript=1">
Contact
May 9, 2024

05/07 - 5/24


  • Penthouse- Framing, Equipment- Connections/Rough MEP Install
  • Spray Fireproofing  (Patching)
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM. 
  • Curtain Wall Installation L16/17-Upcoming
  • Loading Dock- Structure and MEPFP Install
  • Lobby Rough MEP & Framing- Core Wall and Dome Ceiling
  • Lobby Storefront Glass Install
  • Elevators- Service Cars and Low Rise Ongoing, High Rise Enabling Work
  • Recharge System #2- Test Boring Mast Arm Foundation

 

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • MEP Installation Pedestrian Bridge 5/8 & 5/9