Contact
May 4, 2023

05/01-05/12

  • Grade beams complete – continue utilities connections on site.
  • Continue Level 02 south framing (see below re: Ramp F traffic impacts)
  • Start assembly of West and North arch.
  • Continue steel assembly / detailing at Levels 03-04.
  • Starting structural steel at Triangle Parcel.

Night & Weekend Work:

  • RAMP F CLOSURES: 11pm-5am Weeknights Only.(Monday, Tuesday, Wednesday, Thursday)
    • See Traffic Advisory, to be updated weekly.

  • Suffolk/Pembroke to review cut & cap impacts (status of Seaport West, Seaport Hotel, Seaport East?)
  • Delivery of Triangle Steel scheduled for week of May 1st
  • Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated on Saturdays.