3/26 - 4/12


  • Penthouse Equipment deliveries/hoisting
  • Spray Fireproofing  (Patching, Triangle)
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM. 
  • Curtain Wall Installation L12&13&14
  • Spray Insulation Application- Loading Dock & Penthouse
  • Lobby MEP Installation
  • Lobby Rough Framing- Core Wall and Dome Ceiling
  • Elevators- Service Cars Ongoing, Mid and High Rise Enabling Work

 

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.