06/26 - 07/07

  • Continue Level 04 framing
  • Complete Steel Framing & Decking through Level 04
  • Complete Concrete Placement through Level 02
  • Continue Steel Framing through Level 05
  • Finish pouring Level 02 deck
  • Finish Slab on Grade @ Triangle Parcel
  • Complete Groundwater Recharge System
  • See night/weekend schedule below for look-ahead related to traffic & noise impacts.


Night & Weekend Work:

  • Ted Williams Tunnel is closed overnight for re-paving work by MassDOT this week. 10 World Trade project overhead protection at top of Ramp F is scheduled to be completed by Thursday 06/29 while this operation is happening concurrently.
  • Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected.