1/29 - 2/9


  • Elevator Support Steel Installation
  • Slab on Deck reinforcements and MEP penetrations (roof level)
  • Concrete Slab on Deck Placements (roof level)
  • Spray Fireproofing  (Dome Ceiling)
  • Mechanical / Elevator shaft framing
  • Rough Mechanical Installation
  • Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM.
  • Curtain Wall Installation (Levels 08-09)
  • Spray Insulation Application- Dome Ceiling and Loading Dock
  • Concrete placement – Level 01+Mezzanine

 

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • One Additional Hoist Jump Upcoming- Roof Access- Date TBD
  • Tower Crane Dismantle (Local Traffic Impacts – March 2024, details pending)