<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=459021408546817&amp;ev=PageView&amp;noscript=1">
Contact
Jan 4, 2024

1/2 - 1/12


  • Steel Detailing (roof level)
  • Elevator Support Steel Installation
  • Slab on Deck reinforcements and MEP penetrations (roof level)
  • Concrete Slab on Deck Placements (roof level + mezzanine)
  • Spray Fireproofing (level 16)
  • Curtain Wall Installation (level 05-06)
  • Spray Insulation Application- Dome Ceiling and Loading Dock

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • One Additional Hoist Jump Upcoming- Roof Access- Date TBD