6/17/24 - 6/28/24
Penthouse- Framing, Equipment- Connections/Rough MEP Install Mechanical Riser Install/Shaft Framing Rough Mechanical Installation Triangle Geofoam...
Continue steel assembly / detailing at Levels 2 - 3.
Continued below-grade work throughout Triangle Parcel.
Form & pour concrete wall at Triangle Parcel.
No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete impacts)
Night work for steel and utilities likely for weeks of April 18th – May 5th.
Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated on Saturdays.
Next Construction Holiday: Monday April 17th (Patriot’s Day / Marathon Monday)