Construction Updates | 10 World Trade
09/05 - 09/15
Written by
Author Name
| 9/7/23 6:30 PM
Complete Steel Framing & Decking through Level 13
Complete Concrete Placement through Level 08
Pour concrete @ Basement
Continue spray Fireproofing of lower levels
Continue prep for landscape @ Triangle Parcel & WTC Ave
Continue installation of intumescent paint
Continue installation of construction hoist @ WTC Avenue
Night & Weekend Work:
Welding at Pedestrian Bridge structure (Ramp F closure, weeknights 11pm-5am)
Target start Monday 9/11, target completion Friday 9/15
Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected
Upcoming Holidays:
Monday October 9
th
(Columbus Day)