Construction Updates | 10 World Trade

09/05 - 09/15

Written by Author Name | 9/7/23 6:30 PM
  • Complete Steel Framing & Decking through Level 13
  • Complete Concrete Placement through Level 08
  • Pour concrete @ Basement
  • Continue spray Fireproofing of lower levels
  • Continue prep for landscape @ Triangle Parcel & WTC Ave
  • Continue installation of intumescent paint
  • Continue installation of construction hoist @ WTC Avenue

Night & Weekend Work:

  • Welding at Pedestrian Bridge structure (Ramp F closure, weeknights 11pm-5am)
    • Target start Monday 9/11, target completion Friday 9/15
  • Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected

Upcoming Holidays:

  • Monday October 9th (Columbus Day)