Construction Updates | 10 World Trade

09/18 - 09/29

Written by Author Name | 9/21/23 6:00 PM
  • Complete Steel Framing & Decking through Level 14
  • Complete Concrete Placement through Levels 10-11
  • Pour concrete @ Slab on Grade & Mezzanine
  • Continue Intumescent Paint & Spray Fireproofing of lower levels (01-04)
  • Continue prep for landscape @ Congress Street & WTC Ave
  • Continue prep for curtainwall through Level 09
  • Complete installation of construction hoist @ WTC Avenue
  • Eversource Permanent Power installation @ Congress Street: awaiting confirmation of timing.

Night & Weekend Work:

  • Saturday Day Shift Work to be requested on case-by-case basis. 
  • Fire Protection piping in Congress St @ Triangle Parcel:
    • 10pm-4am, Sunday night through Thursday night. Complete by 4am Friday 9/22.

  • Pedestrian Bridge Steel welding: Thursday 9/21 (11pm-5am). Ramp F closed to traffic.Night & Weekend Work:

 

Upcoming Holidays:

  • Monday October 9th: Columbus Day.