Complete Steel Framing & Decking through Level 14
Complete Concrete Placement through Levels 10-11
Pour concrete @ Slab on Grade & Mezzanine
Continue Intumescent Paint & Spray Fireproofing of lower levels (01-04)
Continue prep for landscape @ Congress Street & WTC Ave
Continue prep for curtainwall through Level 09
Complete installation of construction hoist @ WTC Avenue
Eversource Permanent Power installation @ Congress Street: awaiting confirmation of timing.
Night & Weekend Work:
Saturday Day Shift Work to be requested on case-by-case basis.
Fire Protection piping in Congress St @ Triangle Parcel:
10pm-4am, Sunday night through Thursday night. Complete by 4am Friday 9/22.
Pedestrian Bridge Steel welding: Thursday 9/21 (11pm-5am). Ramp F closed to traffic.
Night & Weekend Work:
Upcoming Holidays:
Monday October 9
th
: Columbus Day.