- Complete Steel Framing & Decking through Level 16
- Complete Concrete Placement through Levels 11-12
- Continue Intumescent Paint & Spray Fireproofing of lower levels (through Level 06)
- Continue prep for landscape @ Congress Street & WTC Ave
- Continue prep for curtainwall through Level 13
- Eversource Permanent Power installation @ Congress Street: awaiting confirmation of timing.
- Water utilities work to start approx. 10/10 outside Seaport West (daytime hours).
Night & Weekend Work:
- Saturday Day Shift Work to be requested on case-by-case basis.
- Fire Protection piping in Congress St @ Triangle Parcel: complete
- Pedestrian Bridge Steel welding: complete
Upcoming Holidays:
- Monday October 9th: Columbus Day.