Construction Updates | 10 World Trade
10/30 - 11/10
Written by
Author Name
| 11/2/23 6:00 PM
Steel framing complete through roof
Install Monument Stair between Levels 01-02
Complete Concrete Placement through Level 14
Continue Intumescent Paint & Spray Fireproofing of lower levels (through Level 11)
Continue prep for curtainwall through Level 15
Eversource Permanent Power installation @ Congress Street: awaiting confirmation of timing.
Work expected to be complete before November 15
th
Continue MEP riser installations in building core through Level 11
Night & Weekend Work:
Overnight cut & cap of water service (Seaport Hotel) was completed Monday 10/30
Overnight cut & cap of fire protection service (Seaport Hotel) is TBD.
Saturday Day Shift Work to be requested on case-by-case basis.
Upcoming Holidays:
Thanksgiving: Thursday November 23, 2023