Construction Updates | 10 World Trade
10/23-11/03
Written by
Author Name
| 10/26/23 5:30 PM
Complete Steel Framing & Decking through Roof
Topping Out Ceremony to take place Thursday 10/26: 11am-1pm @ WTC Ave Plaza
Install Monument Stair between Levels 01-02
Complete Concrete Placement through Level 13
Continue Intumescent Paint & Spray Fireproofing of lower levels (through Level 11)
Continue prep for curtainwall through Level 14
Eversource Permanent Power installation @ Congress Street: awaiting confirmation of timing.
Work expected to be complete before November 15
th
Continue MEP riser installations in building core through Level 10
Night & Weekend Work:
Overnight cut & cap of water / sprinkler service
(Seaport West/Hotel): Monday 10/30 (11pm-5am)
.
Saturday Day Shift Work to be requested on case-by-case basis.
Upcoming Holidays:
Thanksgiving: Thursday November 23, 2023