Steel/Deck Erection
(18 Metal Decking, 18&19 framing)
Slab on Deck reinforcements and MEP penetrations (L16 and L17)
Concrete Slab on Deck Placements (L15 North and L16 South)
Continue Intumescent Paint & Spray Fireproofing of lower levels (through L13)
Continue prep for curtainwall through L17
Continue MEP riser installations in building core
Night & Weekend Work:
Saturday Day Shift Work to be requested on case-by-case basis.
Permanent Power Install - Eversource