Construction Updates | 10 World Trade

05/08-05/19

Written by Author Name | 5/11/23 6:00 PM
  • Grade beams complete – continue utilities connections on site.
  • Continue Level 02 south framing (see below re: Ramp F traffic impacts)
  • Complete detailing of West arch

  • Start assembly of North arch

  • Continue steel assembly on Triangle Parcel


Night & Weekend Work:

  • RAMP F CLOSURES: 11pm-5am Weeknights Only.(Monday, Tuesday, Wednesday, Thursday)
    • Completion of Level 02 decking anticipated by 5am Thursday May 11th.
    • See Traffic Advisory, to be updated weekly.

  • Suffolk/Pembroke to review cut & cap impacts (status of Seaport West, Seaport Hotel, Seaport East?)
  • Congress Street detour scheduled for 11pm Friday May 19th though 11pm Sunday May 21st.

    • Traffic Advisory to be distributed by May 10th.

  • Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated on Saturdays.