- Penthouse- Framing, Equipment- Connections/Rough MEP Install
- Spray Fireproofing (Patching)
- Mechanical Riser Install/Shaft Framing
- Rough Mechanical Installation
- Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM.
- Curtain Wall Installation L16/17-Upcoming
- Loading Dock- Structure and MEPFP Install
- Lobby Rough MEP & Framing- Core Wall and Dome Ceiling
- Lobby Storefront Glass Install
- Elevators- Service Cars and Low Rise Ongoing, High Rise Enabling Work
- Recharge System #2- Test Boring Mast Arm Foundation
Night & Weekend Work:
- Saturday Day Shift Work to be requested on case-by-case basis.
- MEP Installation Pedestrian Bridge 5/8 & 5/9