- Penthouse- Framing, Equipment- Connections/Rough MEP Install
- Mechanical Riser Install/Shaft Framing
- Rough Mechanical Installation
- Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM.
- Curtain Wall Installation L16/17-Upcoming
- Loading Dock- Structure and MEPFP Install
- Lobby Rough MEP & Framing- Core Wall and Dome Ceiling
- Lobby Storefront Glass Install
- Elevators- Service Cars and Low Rise Ongoing, High Rise Enabling Work
- Recharge System #2
Night & Weekend Work:
- Saturday Day Shift Work to be requested on case-by-case basis.
- Week of 5/28: Ramp F Closures Wed/Thurs 11pm-5am