Construction Updates | 10 World Trade

03/06-03/17

Written by Author Name | 3/9/23 7:30 PM
  • Tower Core Wall Reinforcement & Installation (Level 17-Roof)
  • Steel arch assembly for South Arch (opposite Congress Street)
  • Steel frame erection of Level 01 and 1-Mezzanine
  • Install pile caps & gradebeams on Parcel A-2 & Triangle Parcel.
  • Waterproofing of below-grade elements.
  • Continued installation of utilities within both parcels.

Night Work:

  • No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no noise impacts)

Weekend Work:

            Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated.

Union Construction Holidays (No Work On Site):

            Next Construction Holiday: Monday April 17th (Patriot’s Day / Marathon Monday)