- Continue below-grade work along west and north of A-2 site.
- Continue assembly of East arch (alongside WTC Ave).
- Continue steel assembly / detailing at Levels 1M + 2.
- Start assembly of West arch.
- Pour core slabs Levels 03-05.
- Continued below-grade work throughout Triangle Parcel.
- Form & pour concrete wall at Triangle Parcel.
Night WorK:
- No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no noise impacts)
Weekend Work:
Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated.
UNION CONSTRUCTION HOLIDAYS (No Work On Site):
Next Construction Holiday: Monday April 17th (Patriot’s Day / Marathon Monday)