03/20-03/31

Written by Author Name | 3/23/23 5:30 PM
  • Continue below-grade work along west and north of A-2 site.
  • Continue assembly of East arch (alongside WTC Ave).
  • Continue steel assembly / detailing at Levels 1M + 2.
  • Start assembly of West arch.
  • Pour core slabs Levels 03-05.
  • Continued below-grade work throughout Triangle Parcel.
  • Form & pour concrete wall at Triangle Parcel.

Night WorK:

  • No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no noise impacts)

Weekend Work:

            Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated.

UNION CONSTRUCTION HOLIDAYS (No Work On Site):

            Next Construction Holiday: Monday April 17th (Patriot’s Day / Marathon Monday)