Construction Updates | 10 World Trade

02/27-03/10

Written by Author Name | 3/3/23 11:45 PM
  • Continue installation of pile caps, waterproofing, and grade beams
  • Concrete Tower Core (Levels 13-16)

  • Steel arches have arrived! Assembly starting along south side (opposite Congress Street)

  • Continued utilities work on Triangle Parcel

  • Continued installation of grade beams in preparation for steel structure on Triangle Parcel

Night Work:

  • No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no noise impacts)

Weekend Work:

            Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated.

Union Construction Holidays (No Work On Site):

            Next Construction Holiday: Monday April 17th (Patriot’s Day / Marathon Monday)