Continue below-grade work along west and north of A-2 site.
Prepare for assembly of East arch (alongside WTC Ave).
Continue steel assembly / detailing at Levels 1M + 2.
Pour core slabs Levels 03-05.
Continued below-grade work throughout Triangle Parcel.
Pour concrete wall at Triangle Parcel.
Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated.
Next Construction Holiday: Monday April 17th (Patriot’s Day / Marathon Monday)