Construction Updates | 10 World Trade

3/12 - 3/29

Written by Author Name | 3/14/24 5:45 PM

  • Penthouse Equipment deliveries/hoisting
  • Spray Fireproofing  (Patching, Triangle)
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM. 
  • Curtain Wall Installation L12&L13
  • Spray Insulation Application- Loading Dock/Penthouse
  • Lobby MEP Installation
  • Lobby Rough Framing- Core Wall and Dome Ceiling
  • Auditorium MEP Install and Ceiling Framing

 

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • Tower Crane Dismantle- Targeting Friday 3/29.