  • Penthouse- Framing, Equipment- Connections/Rough MEP Install
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • Triangle Geofoam Placement/Switchback Ramp FRP/Waterproofing
  • Curtain Wall Installation L16/17-Upcoming
  • Loading Dock- Structure and MEPFP Install
  • Lobby Rough MEP & Framing- Core Wall and Dome Ceiling
  • Lobby Storefront Glass Install
  • Elevators- Service Cars and Low Rise Ongoing, High Rise Enabling Work
  • Recharge System #2
  • WTC Ave Demo/Hardscape

 