- Continue Level 04 framing
- Complete Steel Framing & Decking through Level 04
- Complete Concrete Placement through Level 02
- Continue Steel Framing through Level 05
- Finish pouring Level 02 deck
- Finish Slab on Grade @ Triangle Parcel
- Complete Groundwater Recharge System
- See night/weekend schedule below for look-ahead related to traffic & noise impacts.
Night & Weekend Work:
- Ted Williams Tunnel is closed overnight for re-paving work by MassDOT this week. 10 World Trade project overhead protection at top of Ramp F is scheduled to be completed by Thursday 06/29 while this operation is happening concurrently.
- Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected.
- Holidays: No Work on site for Tuesday July 4th.