6/17/24 - 6/28/24

Written by Author Name | 6/20/24 6:00 PM

 

  • Penthouse- Framing, Equipment- Connections/Rough MEP Install
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • Triangle Geofoam Placement/Switchback Ramp FRP/Waterproofing
  • Curtain Wall Installation L16/17-Upcoming
  • Loading Dock- Structure and MEPFP Install
  • Lobby Rough MEP & Framing- Core Wall and Dome Ceiling
  • Lobby Wood Ceiling Install
  • Elevators- Service Cars, Low Rise, and High Rise Ongoing
  • Recharge System #2
  • WTC Ave Demo/Hardscape

 

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • Week of 6/17- M-Th Ramp D Closures- Triangle Façade Installation