Construction Updates | 10 World Trade

07/24 - 08/04

Written by Author Name | 7/27/23 6:00 PM

  • Complete Steel Framing & Decking through Level 07
  • Complete Concrete Placement through Levels 02
  • Form & pour Level 03 deck
  • Excavation for Basement along Congress Street
  • Start Spray Fireproofing of lower levels
  • Finish underground utilities on tower parcel
  • Form & pour tree pits for Triangle Parcel landscape
  • See night/weekend schedule below for look-ahead related to traffic & noise impacts.

Night & Weekend Work:

  • No road / lane closures during Sumner Tunnel Rehabilitation Project (July 1 – September 1)
  • Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected.