- Complete Steel Framing & Decking through Level 06
- Complete Concrete Placement through Levels 02
- Complete Steel Framing through Level 07
- Form & pour Level 03 deck
- Excavation for Basement along Congress Street
- Start demolition of WTC Avenue crash barriers within Project fenceline
- Start Spray Fireproofing of lower levels
- See night/weekend schedule below for look-ahead related to traffic & noise impacts.
Night & Weekend Work:
- No road / lane closures during Sumner Tunnel Rehabilitation Project (July 1 – September 1)
- Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected