- 01/30-02/10
- Triangle Parcel:
- Continued utilities work
- Continued installation of grade beams in preparation for steel structure
â—‹ Parcel A-2:
-
- Continue installation of pile caps, waterproofing, and grade beams
- Concrete Tower Core (target first 100ft vertical by early February)
- Steel arches tracking for mid-February delivery
- Night Work:
-
- No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no noise impacts)
- Weekend Work:
-
- Saturday day shifts to be requested on case-by-case basis, and limited to daytime hours only with no noise or traffic impacts permitted.
- Union Construction Holidays (No Work On Site):
-
- Monday February 20th (Presidents’ Day)