02/21-03/03
Triangle Parcel:
- Continued utilities work
- Continued installation of grade beams in preparation for steel structure
Parcel A-2:
- Continue installation of pile caps, waterproofing, and grade beams
- Concrete Tower Core (Levels 11-15)
- Steel arches tracking for end-February delivery (assembly starts 1st week March)
Night Work:
- No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no noise impacts)
Weekend Work:
Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated.
Union Construction Holidays (No Work On Site):
Next Construction Holiday: Monday April 17th (Patriot’s Day / Marathon Monday)