Construction Updates | 10 World Trade

UPCOMING WORK

Written by Author Name | 2/21/23 5:00 PM

02/13-02/24

Triangle Parcel:

  • Continued utilities work
  • Continued installation of grade beams in preparation for steel structure

Parcel A-2:

  • Continue installation of pile caps, waterproofing, and grade beams
  • Concrete Tower Core (Levels 9-12)
  • Steel arches tracking for end-February delivery (assembly starts 1st week March)

Night Work:

  • No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no noise impacts)

Weekend Work:

  • â—‹Saturday 6am-6pm jumping of the tower crane. No impacts to noise / traffic expected.

Union Construction Holidays (No Work On Site):

  • Monday February 20th (Presidents’ Day)