UPCOMING WORK
Written by
Author Name
| 2/21/23 5:00 PM
02/13-02/24
Triangle Parcel:
Continued utilities work
Continued installation of grade beams in preparation for steel structure
Parcel A-2:
Continue installation of pile caps, waterproofing, and grade beams
Concrete Tower Core (Levels 9-12)
Steel arches tracking for end-February delivery
(assembly starts 1
st
week March)
Night Work:
No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no noise impacts)
Weekend Work:
â—‹
Saturday 6am-6pm jumping of the tower crane. No impacts to noise / traffic expected.
Union Construction Holidays (No Work On Site):
Monday February 20
th
(Presidents’ Day)
View full post