02/06-02/17
Triangle Parcel:
- Continued utilities work
- Continued installation of grade beams in preparation for steel structure
Parcel A-2:
- Continue installation of pile caps, waterproofing, and grade beams
- Concrete Tower Core (Levels 7-9)
- Steel arches tracking for end-February delivery
Night Work:
- No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no noise impacts)
Weekend Work:
- Saturday day shifts to be requested on case-by-case basis, and limited to daytime hours only with no noise or traffic impacts permitted.
Union Construction Holidays (No Work On Site):
- Monday February 20th (Presidents’ Day)