UPCOMING WORK

Written by Author Name | 2/9/23 7:00 PM

02/06-02/17

Triangle Parcel:

  • Continued utilities work
  • Continued installation of grade beams in preparation for steel structure

Parcel A-2:

  • Continue installation of pile caps, waterproofing, and grade beams
  • Concrete Tower Core (Levels 7-9)
  • Steel arches tracking for end-February delivery

Night Work:

  • No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no noise impacts)

Weekend Work:

  • Saturday day shifts to be requested on case-by-case basis, and limited to daytime hours only with no noise or traffic impacts permitted.

Union Construction Holidays (No Work On Site):

  • Monday February 20th (Presidents’ Day)