- Concrete Slab on Deck Placements (roof level)
- Spray Fireproofing (Dome Ceiling)
- Mechanical / Elevator shaft framing
- Lobby MEPs
- Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM.
- Curtain Wall Installation (Levels 09-10)
- Spray Insulation Application- Dome Ceiling and Loading Dock
- Concrete placement – Grand Staircase
Night & Weekend Work:
- Saturday Day Shift Work to be requested on case-by-case basis.
- Removal of South Protective Deck (Local Traffic Impacts -- March 2024, details pending)
- Tower Crane Dismantle (Local Traffic Impacts – March 2024, details pending)