2/26 - 3/15

Written by Author Name | 2/29/24 6:30 PM

  • Penthouse Equipment deliveries/hoisting
  • Spray Fireproofing  (L18, Triangle)
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM. 
  • Curtain Wall Installation L11&L12
  • Spray Insulation Application- Loading Dock
  • Lobby MEP Installation
  • Lobby Rough Framing- Core Wall and Dome Ceiling

 

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • Tower Crane Dismantle- Planning for weekend of 3/15