Steel/Deck Erection (roof decking & framing)
Slab on Deck reinforcements and MEP penetrations (L17)
Concrete Slab on Deck Placements (L17 South and L17 North)
Spray Fireproofing (L13, L1-L3)
Curtain Wall Installation (L2-L4)
Triangle Foundation Wall Placements
Night & Weekend Work:
Saturday Day Shift Work to be requested on case-by-case basis.
Planned Night Work: Second Shift of hoist jump scheduled for 12/11-12/15
Upcoming Holidays:
Christmas Day: Monday December 25, 2023