Construction Updates | 10 World Trade
08/14 - 08/25
Written by
Author Name
| 8/17/23 6:00 PM
Complete Steel Framing & Decking through Level 10
Complete Concrete Placement through Level 07
Start concrete @ Auditorium seating
Continue excavation for Basement along Congress Street
Continue spray Fireproofing of lower levels
Continue prep for landscape @ Triangle Parcel & WTC Ave
See night/weekend schedule below for look-ahead related to traffic & noise impacts.
Night & Weekend Work:
No road / lane closures during Sumner Tunnel Rehabilitation Project (July 1 – September 1)
Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected
Upcoming Holidays:
Labor Day - Monday September 4