08/28 - 09/08
Written by
Author Name
| 8/31/23 6:00 PM
Complete Steel Framing & Decking through Level 12
Complete Concrete Placement through Level 08
Pour concrete @ Basement
Continue spray Fireproofing of lower levels
Continue prep for landscape @ Triangle Parcel & WTC Ave
Continue installation of intumescent paint
Continue installation of construction hoist @ WTC Avenue
Night & Weekend Work:
No road / lane closures during Sumner Tunnel Rehabilitation Project (July 1 – September 4)
Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected.
Upcoming Holidays:
Labor Day - Monday September 4