- Complete Steel Framing & Decking through Level 08
- Complete Concrete Placement through Levels 04
- Excavation for Basement along Congress Street
- Start Spray Fireproofing of lower levels
- Form & pour tree pits for Triangle Parcel landscape
- Continue hardscape work @ WTC Ave
- See night/weekend schedule below for look-ahead related to traffic & noise impacts.
Night & Weekend Work:
- No road / lane closures during Sumner Tunnel Rehabilitation Project (July 1 – September 1)
- Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected
- Eversource work @ Haul Rd (back of house Omni Hotel): coordination ongoing.