04/03-04/13

Written by Author Name | 4/26/23 6:00 PM
  • Continue below-grade work along west and north of A-2 site.
  • Continue steel assembly / detailing at Levels 2 - 3.

  • Continued below-grade work throughout Triangle Parcel.

  • Form & pour concrete wall at Triangle Parcel.

Night Work:

No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete impacts)

Night work for steel and utilities likely for weeks of April 18th – May 5th.

 

Weekend Work:

Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated on Saturdays.

 

Union Construction Holidays (No Work On Site):

Next Construction Holiday: Monday April 17th (Patriot’s Day / Marathon Monday)