Construction Updates | 10 World Trade
04/24-05/05
Written by
Author Name
| 4/26/23 6:32 PM
Grade beams complete – continue utilities connections on site.
Continue Level 02 south framing (see below re: Ramp F traffic impacts)
Start assembly of West arch
Continue steel assembly / detailing at Levels 03-04.
Continue below-grade & prepare for structural steel at Triangle Parcel.
Night & Weekend Work:
RAMP F CLOSURES: 11pm-5am Weeknights Only.
(Monday, Tuesday, Wednesday, Thursday)
See Traffic Advisory, to be updated weekly.
Suffolk/Pembroke to review cut & cap impacts (status of Seaport West, Seaport Hotel, Seaport East?)
Delivery of Triangle Steel scheduled for week of May 1
st
. Night shift to be confirmed.
Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated on Saturdays.