- Patriots’ Day / Marathon Monday (04/17): No work on site.
- Continue below-grade work along west and north of A-2 site.
- Continue steel assembly / detailing at Level 03.
- Continue below-grade & prepare for structural steel at Triangle Parcel.
Night Work:
- RAMP F CLOSURES: 11pm-5pm Weeknights Only. Starting Wednesday 04/19/23.
- Congress Street Utilities Work: Possible Start Monday night 04/24
- Suffolk/Pembroke to review cut & cap impacts Thursday 04/20 @ 09:30am.
Weekend Work:
- Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated on Saturdays.